KUMTOR ANNOUNCES A BID PROCESS FOR EARTHWORKS DURING CONSTRUCTION OF THE TAILINGS FACILITIES

KUMTOR ANNOUNCES A BID PROCESS FOR EARTHWORKS DURING CONSTRUCTION OF THE TAILINGS FACILITIES

published: 02 November 2018

DEADLINE HAS EXPIRED

KUMTOR GOLD COMPANY CJSC (KGC) announces a bid process for performance of earthworks during construction of tailings facilities with an approximate start date of 15 March 2019, and an approximate end date of 31 October 2020. During the winter season from approximately 1 November 2019 to 15 March 2020 operations will be suspended and contractors will remove their equipment from site.

– Total calculated volume of excavation works for 2019 is approximately 1, 060,000 m3 of soil for quality filling of the buttress above the shear key with soil compaction of 2.1 g/cm3 at an average one-way hauling distance of up to 5.4 km and approximately 170,000 m3 of soil (excavation, levelling, bedding, backfilling, transportation) at an average one-way hauling distance of up to   3.0 km in Petrov Lake area.

– Total calculated volume of excavation works for 2020 is approximately 1,050,000 m3 of soil is for quality filling of the buttress above the shear key with soil compaction of 2.1 g/cm3 at an average one-way hauling distance of up to 5.4 km and approximately 170,000 m3 of soil (excavation, levelling, , bedding, backfilling, transportation) at an average one-way hauling distance of up to 3.0 km in Petrov Lake area.

Interested organizations and private entrepreneurs with a fleet of its own equipment are welcome to submit technical and commercial proposals in a sealed A4 envelope marked “Construction of tailings facilities – 2019 / 2020” to the 10th floor of Uchkun building in Bishkek at 24 Ibraimov Street to the attention of the Selection Committee by 5 p.m. on November 30, 2018.

RequireD equipment FOR 2017*:

  • Dump trucks 25t – 25 units
  • Front-end loaders 3.0 m3 – 3 units
  • Bulldozers B10, B12 or equivalent – 4units
  • Bulldozers D8 and D9 – 2 units
  • Excavators CAT325 or Volvo EC3000L – 2 units
  • Vibrating roller 18t or heavier – 5 units
  • Water trucks 10-15t, wheel formula 4×6 or 6×6 – 2 units

 

*- Required equipment for 2020 will be determined according to 2020 Total calculated volume of excavation works for 2020.

 

Operating schedule – 11-hour day and night shifts (22 hours per day). Only minor repairs of equipment are allowed at the Kumtor Mine site. Equipment downtime due to weather conditions or repair shall not be compensated. Mobilization and demobilization of equipment shall be made at the cost of the bidder. Transportation of the bidder’s personnel from and to Kumtor Mine is also at the cost of the bidder.

KGC commitments:

Providing the personnel of the bidder with accommodations and board at the Kumtor Mine site and fuel for operation of the equipment.

requirements TO Commercial proposalS:

The bid shall include the following:

  • portfolio of the company or private entrepreneur (copies of the registration certificate, charter, available permits and licenses, tax parameters of the tax payer, list of business partners with a brief description of accomplished works and references);
  • information about proposed equipment (type, quantity, registration documents, maintenance history, pictures), including stand-by equipment;
  • information on the company headquarters, principal home depot and regional fleet yards;
  • all-inclusive proposed BCM rates for actually transported, loaded, leveled, watered and compacted material by the above listed equipment (all applicable taxes and deductions, mobilization and demobilization of equipment; depreciation of equipment, work of full-time foreman and mechanic, operation of the foreman’s vehicle, PPE, salaries + allowances and bonuses, sick-leaves, overhead costs, profit, etc.);
  • information on employees and key officers with a description of their work experience;
  • any additional terms, which the bidder may find appropriate and necessary.

All bidders submit their bids at their own will, at their own costs, and accept all KGC conditions. No claims for compensation of any costs of the bidder shall be accepted by KGC. Site visits are not anticipated. Any additional information or clarifications can be requested via e-mail: kumtor.localbuyer@centerragold.com.

KGC reserves the right to accept or reject a bid in full or in part, and make a selection of the most competitive bidders at KGC’s choice. KGC explicitly intends to split this work between several bidders, and do not enter into a contract with one bidder. KGC will prioritize contractor organizations from the local region (Jety-Oguz, Ton and Balykchy) provided they have the required capability. KGC will notify only preselected bidders.